UPDATE THE CONSTRUCTION PROGRESS OF KTG BAC NINH INDUSTRIAL AND WAREHOUSE CENTER FOR PERIOD B – NOVEMBER 30TH, 2019

By the end of November 2019, most of the frame of works of KTG Bac Ninh Industrial and Warehouse Center stage B were almost erected. The construction unit is actively completing the project to keep pace with hand-over schedule to customers.

KTG Bac Ninh Industrial and Warehouse Center stage 2 started construction in July 2019, up to now, the frame of the blocks of KTG Bac Ninh Industrial and Warehouse Center has almost been erected. Engineers and workers are still working hard to ensure the project progress. Up to the present time, the construction progress is still taking place according to the original plan.

KTG Bac Ninh Industrial and Warehouse Center stage B is located at National Highway 18, Dong Yen Hamlet, Dong Phong Commune, Yen Phong District, Bac Ninh with a total scale of 60,000 square meters. Upon launch, the project has received the trust of customers. Currently, block 3 and 4 of the project has been trusted by Kostate Inc. – a manufacturer of phone accessories from Korea. Regardless of the expectation and trust of customers, the construction unit is still rushing to ensure the project progress and is expected to be handed over by the end of the fourth quarter of 2019.

Update the main tasks at the project until November 30th, 2019:

 